Understanding Building Safety Regulator (BSR) Compliance
For building owners, clients, managing agents, factors and duty holders. Who is responsible, which approval route applies and what evidence you need, from the Building Safety Regulator in England to building warrants in Scotland and the new regime in Wales. Written by the team that prepares Building Safety Regulator submissions and delivers building envelope remediation.
Five things to establish before work begins
These points apply in all three countries. The chapters below explain how each one works in England, Scotland and Wales.
- Identify the country and the decision you need to make. Building control, occupied-building duties, cladding assessment and funding can each use a different test.
- Record who holds each responsibility. The client, owner, principal duty holders, factor and Building Safety Manager are not interchangeable roles.
- Obtain the required approval before the relevant work starts. Funding, planning permission and a submitted application do not replace it.
- Investigate the building and keep evidence as work proceeds. Assess changes before they are made and inspect key details before they are covered.
- Plan for the people in the building and for its future. Resident information, safety during the works and a usable handover belong in the project from the start.
Choose your country
Each country chapter is a complete route on its own. Chapters 01, 02 and 06 to 09 apply in all three countries.
Northern Ireland and the Republic of Ireland have their own systems and are outside the scope of this guide. It gives general information and cannot decide a building's legal classification or replace advice on a specific property.
In this guide
Nine chapters, from finding the right system to planning your next step. Use the Contents button at any point to jump between them.
Which building safety system applies
Start with where the building stands and what you are trying to do. A building control test decides the process for building work, while a cladding programme or funding threshold answers a different question. Use the rules of the country the building is in before choosing a route.
Planning work to a building starts with knowing which rules apply. The country matters, but so do the building's use, the proposed work and whether people will stay in the building while it happens. A height threshold or a job title on its own will not answer those questions.
A building control test decides the approval process for building work. A cladding programme or funding threshold answers a different question. Being below a height threshold does not remove building standards, fire safety, housing or construction health and safety responsibilities.
Thresholds only make sense with a purpose
In England, the higher-risk building test for building work combines a height of at least 18 metres or at least seven storeys with at least two residential units, or a qualifying hospital or care home. The test for occupied buildings is different.
In Wales, the same height or storey threshold applies, but the use test includes buildings with at least one residential unit and children's homes. Scotland has no equivalent higher-risk building test for building work. Its cladding programme uses an 11 metre threshold with further conditions, and its Compliance Plan Approach guidance uses a different scope again.
English leaseholder protections and Welsh remediation funding also use tests linked to 11 metres. Those tests do not mean the English or Welsh higher-risk building control route applies.

What to establish about your property
- The country and the actual uses of every part of the building
- Measured height and storeys, using the statutory method
- Ownership, connected structures and shared podiums
- The proposed work and any change of use
- Whether people will occupy the building during the work
- A written conclusion from your adviser, reviewed if the scope changes
Three countries, three routes
A summary of the main differences. Each country chapter explains the detail and links to the official guidance.
- AP / PAP
- Accountable Person / Principal Accountable Person (England)
- BAC
- Building Assessment Certificate (England)
- BSR
- Building Safety Regulator (England)
- CPA
- Compliance Plan Approach (Scotland)
- EWS1
- External wall fire review form, used for valuation and lending
- FRAEW
- Fire risk appraisal of external walls
- HRB
- Higher-risk building
- MOR
- Mandatory occurrence reporting
- SBA
- Single Building Assessment (Scotland)
For a portfolio, keep a separate record for each building and each country rather than one generic "UK building safety" checklist.
Who is responsible
Identify responsibilities before procurement. Some arise from ownership or control of a building, others from a statutory appointment. Appointing a consultant or contractor brings expertise, but it does not remove the duties that stay with the client or owner.
The client and the appointed team
A client commissioning work needs to establish the approval route, provide relevant information about the building and allow enough time and resources. Designers need to understand the requirements that apply to their work. Contractors need competent supervision, coordinated information and a way to show that the installed work matches the design.
In England, Building Regulations duty holders work under Part 2A. In Wales, Part 2B duties took effect on 1 July 2026, subject to transitional arrangements. Both include client, designer and contractor duties and principal roles, but their legal application and the additional higher-risk building procedures need checking separately.
Principal roles and CDM
The Principal Designer and Principal Contractor roles under the Building Regulations in England and Wales concern compliance with the Building Regulations. The same titles appear in the Construction (Design and Management) Regulations 2015, which cover construction health and safety across Great Britain. One organisation can hold more than one role if it is competent and properly appointed. Record which regime each appointment sits under and what it covers.
A Scottish project can have CDM principal appointments without being subject to the Building Regulations principal roles that apply in England and Wales. In Scotland, building standards responsibilities sit with the Relevant Person and are checked by the verifier.
Principal Designer and Principal Contractor services
Owners and occupied buildings
England
Accountable Persons (APs) and the Principal Accountable Person (PAP) are identified under the legal tests for occupied higher-risk buildings. Ownership and repairing obligations matter. A managing agent or Building Safety Manager does not automatically become the PAP, and the Responsible Person under fire safety law is a further role.
Scotland
Owners, housing providers and factors need clear arrangements for the building and its shared parts. Identify the factor's authority, the owners' responsibilities and who coordinates fire safety information. The Relevant Person for building standards is a separate project responsibility.
Wales
Identify the client and principal duty holders for the work and the Responsible Person under current fire safety law. The Building Safety (Wales) Act 2026 introduces its own Accountable Person framework in stages, so do not assume England's occupied-building processes already apply.
Checking competence
SKEB means skills, knowledge, experience and behaviours. Ask for evidence that relates to the actual building and role, alongside the organisation's capacity, checking arrangements and access to specialists. Qualifications and memberships support that assessment, but they do not prove suitability for every project.
Read our guide to competence and SKEBAppointing a team does not transfer every duty
- Some duties come from ownership or control of the building
- Others come from a statutory appointment
- A consultant or contractor brings expertise, not the client's or owner's own duties
- Record each appointment in writing, with its legal regime and scope
England and the Building Safety Regulator
Higher-risk building work in England follows a gateway process. Gateway 1 considers fire safety at planning, Gateway 2 is the application the Building Safety Regulator must approve before work starts, and Gateway 3 is the completion process, in which the BSR assesses the evidence and inspects the work before issuing a completion certificate. Separate duties apply to Accountable Persons in occupied buildings.
Check the English building and work definitions
The main threshold for building work is a height of at least 18 metres or at least seven storeys, combined with at least two residential units or a qualifying hospital or care home. Exclusions and legal measurement rules apply. Hotels, for example, are excluded, while student accommodation can be included.
The definition for occupied higher-risk buildings uses the same height or storey threshold with at least two residential units, but excludes hospitals and care homes. Establish both classifications separately.
Schools, offices and industrial buildings outside the higher-risk definition still have safety and approval obligations through local authority building control or a registered building control approver.
The Building Safety Act and our servicesThe gateway process in England
Higher-risk building work in England moves through three gateways. Each is a decision point with its own purpose, decision maker and evidence. Gateway 2 and Gateway 3 are connected: the controls agreed at Gateway 2 produce the evidence that Gateway 3 relies on.
Remediation of an existing, occupied building
Gateway 1 often does not apply, because remediation rarely needs a relevant planning application. Gateway 2 approval covers only the remedial work submitted, so the investigation needs to be complete enough to define it. The BSR looks at whether the work reduces risk without introducing new risk, keeps the building safe while it is occupied and does not rely on decisions left to site.
Gateway 3 still applies. A completion certificate is required when building work to an existing higher-risk building is completed, while residents continue to live in the building.
Gateway 1: planning and the fire statement
For relevant planning applications, planning gateway one requires fire safety to be considered, with a fire statement unless an exemption applies. The BSR is consulted on fire safety and the local planning authority decides the application.
A positive outcome means fire safety is acceptable in principle for planning purposes. It does not approve the building design or confirm that the work will meet the Building Regulations. That is the job of Gateway 2.
Gateway 2: the building control approval application
The client is responsible for obtaining approval from the BSR before the relevant work starts. An acknowledgement or validation of the application is not approval. The client can authorise a representative to manage the application but keeps the legal responsibility.
Work to existing higher-risk buildings is categorised as Category A or Category B. Category A includes remediation to common parts inside or outside the building and work involving active or passive fire safety measures. Check the current guidance for exceptions, scheme work, emergency repairs and transitional projects. The value of a contract does not decide the route.
The BSR assesses evidence, not intent
The decision rests on how compliance will be controlled and evidenced, not just on what is drawn. Every document needs to tell the same story. A contradiction between a drawing, the fire strategy and the materials schedule is a common reason for questions and delay.
What a Gateway 2 application includes
- Detailed drawings and specifications for the work
- A Building Regulations compliance statement explaining how each requirement is met
- Fire strategy, structural and external wall information, with evidence for every material
- A construction control plan and a change control plan
- The client's competence declaration, with supporting competence statements
- Mandatory occurrence reporting arrangements
- A fire and emergency file, depending on the work and route

Coordinated design
Wall types, build-ups and interfaces defined from surveys and the FRAEW, with fire and structural engineers' comments closed out and recorded before submission.
Materials evidence
For each product: the specification, data sheets, certificates and fire classification or test evidence, plus where it is used. If a material cannot be evidenced, it cannot be relied on.
Control documents
A construction control plan and change control plan written for the project, not generic templates. They show how compliance will be managed on site.
Competence
Role-specific evidence for the client, Principal Designer and Principal Contractor. Generic CVs and confusion between CDM and Building Safety Act duties invite challenge.
Starfish Construction also uses an inspection, test and approval plan, a design review tracker and an indexed information schedule to keep the application coordinated. These are good practice rather than named statutory documents.
Plan the programme realistically
The published framework allows eight weeks to assess Gateway 2 applications for existing higher-risk buildings and 12 weeks for new ones, unless extended by agreement. Actual approval times can be longer. Use current BSR performance data for the type of application, and allow time for investigation, design reviews and questions.
A Pre-Construction Services Agreement can structure the investigation, design and cost planning that an application relies on. Approval remains a decision for the regulator.
Changes and inspections
Assess controlled changes against the English criteria. Recordable changes go in the change log. Notifiable changes are submitted before the change or related work is carried out. Major changes, such as a different external wall system, altered fire stopping or a redesign after a structural defect is found, need BSR approval before affected work goes ahead. The statutory target for deciding a major change is six weeks, so thorough investigation before Gateway 2 protects the programme.
Arrange inspections and evidence collection before safety-critical work is covered. Give the required notices: the notice of intention to start at least five working days before work begins, and a separate notice when the defined commencement milestone is reached. A contract variation or a supplier's claim of equivalence does not replace the regulatory process.
Reporting safety occurrences
Principal duty holders must run a mandatory occurrence reporting system for relevant higher-risk building work, and the arrangements form part of the Gateway 2 application. A reportable occurrence is a specified fire or structural safety risk that could cause death or serious injury to a significant number of people.
Where an occurrence is reportable, notify the BSR as soon as possible and submit a written report within ten calendar days of identifying it. Making the issue safe does not remove the duty to report it. After occupation, reporting duties sit with the Accountable Person.
Gateway 3: the completion process
Gateway 3 starts long before the work finishes. The construction control plan, inspection regime and change log agreed at Gateway 2 generate the evidence the BSR needs at completion. If that evidence is not captured as the work goes in, it is very hard to recreate.
Occupied higher-risk buildings
In occupied higher-risk buildings, Accountable Persons assess and manage the risks of fire spread and structural failure in their parts of the building. The Principal Accountable Person has whole-building duties, including registration, the safety case report, resident engagement, complaints and a mandatory occurrence reporting system. A project appointment does not suspend those duties, so coordinate the works with them from the start.
When directed by the BSR, the PAP must apply for a Building Assessment Certificate within 28 days. It concerns compliance with the occupation duties in Part 4 of the Building Safety Act 2022. It is separate from the Gateway 3 completion certificate and does not end ongoing responsibilities.
Residents and personal emergency evacuation plans
Residents need current safety information, a way to raise concerns and meaningful engagement on decisions that affect them. The PAP's resident engagement strategy and complaints process are separate from the contractor's project updates. Residents also have duties, such as not creating significant safety risks or interfering with safety equipment.
England's Residential Personal Emergency Evacuation Plan requirements began in April 2026 for specified residential buildings. Responsible Persons must take reasonable steps to identify residents who may need help to evacuate and offer a person-centred assessment, which residents can choose to take part in. These are England-only regulations.
Our guide to resident and stakeholder engagementFunding and costs
Check developer responsibility, funding eligibility and leaseholder protections separately. New applications for buildings of 11 metres and over use the Cladding Safety Scheme, subject to eligibility. The specific application window for buildings under 11 metres closed on 9 October 2026.
BSR charges for applications and inspections are a further, separate cost. Take advice before allocating costs to leaseholders.
Your English project check
Confirm the building work and occupation classifications, which gateways apply, the principal appointments, any existing AP and PAP arrangements, the application category, the evidence gaps and how Gateway 3 evidence will be captured from day one.
If an urgent risk is identified, protect people and get competent advice. Use the emergency repair procedure where it applies rather than relabelling planned work to avoid approval.
Building Safety Act services Principal Designer and Principal Contractor
JOE FAY
MCIOB MIOR MAPM
PRE-CONSTRUCTION COMPLIANCE & BUILDING SAFETY DIRECTOR
Building safety in Scotland
Scotland uses building warrants, Scottish technical standards and local authority verification. A BSR application cannot replace the owner's or developer's responsibilities there. For cladding concerns, understand the separate Single Building Assessment and remediation arrangements as well as the approvals needed to carry out the work.
Start with the warrant question
Ask the local authority building standards team or your adviser whether the proposed work needs a building warrant. Alterations to roofs, external walls, structure or fire safety measures can need one. Some work does not need a warrant but must still meet the building regulations. A planning decision does not replace a warrant.
For an existing building, the application explains the proposed work and its effect on the building that remains. Investigation establishes the construction, interfaces and constraints the design relies on. Confirm which edition of the Scottish Technical Handbooks applies and any certification arrangements.

Who does what
The Relevant Person
Responsible for compliance and for submitting the completion certificate. Depending on the circumstances, this can be the owner, tenant or developer carrying out or commissioning the work. An agent can help without taking over that responsibility.
The verifier
Normally the local authority. It assesses the warrant application and makes reasonable inquiry about compliance. Verification does not replace the project team's own supervision and quality control.
The factor
Acts within the authority and duties of its appointment. Where a building has several owners, agree decision-making, access, instructions and communication early. Appointing a factor does not remove every owner responsibility.
From warrant to work
Agree the drawings, specifications and calculations the application needs. On complex work, a pre-warrant discussion with the verifier can identify design issues and inspection expectations early. Build time to respond to verifier comments into the programme.
Once the warrant is granted, understand the approved scope and the notification and inspection arrangements, and plan evidence capture around the work sequence. If the design changes, establish whether an amendment to warrant is needed and obtain it before starting the affected work. Agreeing a contract change does not amend a warrant.
The Compliance Plan Approach
Scotland is strengthening verification through the Compliance Plan Approach (CPA). Its guidance asks project teams to plan how compliance will be managed, inspected and evidenced from early design through to completion. At October 2026 it is a guidance approach ahead of planned legislation, rather than a new statutory system like England's.
The guidance covers defined High Risk Buildings and major works, including domestic and residential buildings higher than 11 metres and specified education, community, hospital and residential care buildings. Confirm scope and phasing with the verifier, who decides whether a proposal meets the major works test. These definitions differ from both England's higher-risk buildings and the Scottish cladding programme.
What a Single Building Assessment does
A Single Building Assessment (SBA) examines risks to life created or made worse by an external wall cladding system and identifies mitigation or remediation. The Scottish specification brings external wall appraisal and wider fire risk consideration together. Use the current SBA methodology and competent assessors when a building is in scope.
The programme covers multi-residential buildings at least 11 metres high with an external wall cladding system, built or refurbished between 1 June 1992 and 1 June 2022. Check every condition and the measurement method: height alone is not the full test.
An SBA is not a building warrant, permission to start work or proof that every defect is funded. Its findings should inform the scope, any urgent measures, the specialist design and the right approval route.
Buildings outside the cladding programme, such as offices, schools and industrial premises, can still need investigation, a warrant and specialist fire or structural input. Our Scottish Water RAAC strengthening project shows how survey evidence, structural coordination and controlled work shaped a solution in an operational building.
Funding and the Cladding Assurance Register
The Housing (Cladding Remediation) (Scotland) Act 2024 provides assessment and remediation powers and established the Cladding Assurance Register. An entry records the assessment and relevant remediation information. Check what the entry actually says: it is not an English Building Assessment Certificate or a general building safety certificate.
Where a developer has accepted responsibility, agree the assessment and remediation arrangements with them. Where Scottish Government support applies, get written confirmation of the eligible scope and who will commission the work. The Single Open Call closed on 31 March 2026. Funding separates eligible cladding work from maintenance and other defects, so keep responsibility for anything outside the funded scope visible.
Owners and residents during the process
Agree who communicates with owners and residents, arranges access, collates decisions and keeps the action record. Explain what the assessment has found, what is still uncertain and what happens next. Where several owners or tenures are involved, take advice on authority, consent and cost allocation. A practical first meeting should establish:
Completion is a submission and acceptance process
The Relevant Person submits a completion certificate for warrant work, and the verifier accepts or rejects it after reasonable inquiry. Plan the evidence behind the declaration while the work is under way, including inspections, testing, installed products and certificates. An agent can help prepare the submission, but the responsibility remains.
For new buildings, conversions and extensions, completion must be accepted before occupation or use, unless the verifier has given temporary permission. Alteration work is different: continued occupation is not automatically prohibited, but the completion submission still matters. A contractor's practical completion certificate or an EWS1 form does not replace the Scottish statutory process.
Managing the occupied building
Scotland's fire safety framework differs from England and Wales. Part 3 of the Fire (Scotland) Act 2005 generally concerns non-domestic premises and does not apply to individual flats in the same way, although particular requirements apply to common areas and firefighting facilities. Scottish housing and other legislation also matters, so check the legal basis before using an English Responsible Person or PAP checklist.
For high-rise domestic buildings, Scottish Government guidance recommends clear fire safety management, inspection and maintenance, resident information and control of alterations. Keep shared escape routes clear and maintain fire safety systems through competent arrangements. Changes to flat entrance doors, services or common parts deserve scrutiny, because small alterations can affect compartmentation or escape.
Residents should report building concerns to the owner, landlord, housing provider or factor and keep a record of the response. Building standards questions and potentially dangerous building work go to the local authority. In an emergency, use the building's current emergency instructions and call the emergency services.
Before you close a Scottish project
Confirm that the approved scope and amendments match the completed work, the required inspections and evidence are available, the completion submission has been accepted where required and the people managing the building understand the maintenance and remaining actions. Close the regulatory record and the operational handover together.
Building standards services Façade inspectionsBuilding safety in Wales
Higher-risk building work in Wales follows local authority building control procedures, with a new regime from 1 July 2026. Wales also has its own remediation programme and occupation legislation. Establish which requirements have started and which transitional provisions apply before borrowing an English process.
Check the Welsh building work test
The height or storey threshold is at least 18 metres or at least seven storeys. The use test covers buildings with at least one residential unit, or a qualifying hospital, care home or children's home, subject to exclusions. Check the legal method of measuring the building and how connected parts are treated.
Local authorities administer higher-risk building control in Wales. Other building work has separate approval arrangements. Funding thresholds for residential remediation are different from the higher-risk building test, so a building can be in a remediation programme without meeting the building control definition.

Which version of the process applies
New Welsh higher-risk building procedures and wider duty holder arrangements took effect on 1 July 2026. Earlier plans or notices may fall within transitional provisions. Check the project's application history, scope and dates with the building control authority. A contract award date alone will not decide the route.
Clients and principal duty holders
Part 2B of the Building Regulations sets Welsh duties and competence requirements. The client must make suitable arrangements, provide relevant information about the building, identify higher-risk building work and appoint competent people. Where principal appointments are required, record them in writing and confirm who controls design and construction.
The principal roles concern Building Regulations compliance and are separate from CDM 2015. If the same organisation holds both, record that. The client keeps their own duties even when a representative manages the approval process.
Before starting work
Where the Welsh higher-risk building process requires approval, obtain it before the relevant building work starts. The building control authority assesses the proposed design and how it will be managed. For existing higher-risk buildings, establish the Category A or B route and the information required. Exceptions, emergency repairs and transitional arrangements each need their own check.
The application needs
- Plans and a compliance statement
- Construction control and change control plans
- The client's competence declaration
- Mandatory occurrence reporting arrangements
- A fire and emergency file or Category B fire compliance statement, depending on the route
A programme that allows for decisions
The Welsh framework provides 12 weeks for decisions on new higher-risk buildings and eight weeks for work to existing ones, unless an extension is agreed. These are not site start dates. Agree submission methods and inspection arrangements with the local authority: the English BSR portal is not used in Wales.
A Pre-Construction Services Agreement can organise early investigation, design development and cost planning. Confirm its deliverables for the Welsh route and keep contract milestones separate from statutory approval.
Change control and reporting
Keep the agreed documents current and assess controlled changes under the Welsh rules. Recordable changes are logged. Notifiable changes are submitted before related work. Major changes need approval before they are made or affected work starts. Use the Welsh criteria and authority, even where the terms look like England's.
Principal duty holders must set up a mandatory occurrence reporting system before relevant higher-risk building work begins and keep it running. Notify the building control authority without undue delay and send a written report within ten working days. England's equivalent period is ten calendar days, so build the Welsh deadline into the project's reporting procedure and inductions.
Completion and electronic information
Apply to the Welsh building control authority for the full or partial completion certificate. The submission includes the current agreed documents, change records, duty holder declarations, client confirmation and evidence that information has been handed over to the Responsible Person. Partial completion follows its own strategy and process.
Welsh golden thread guidance requires building information to be kept electronically, accurate, readable, secure and transferable. Agree who will maintain it and check the recipient can use it. England's completion service and Building Assessment Certificate process do not apply.
Occupation law is a separate strand
The Building Safety (Wales) Act 2026 sets up an occupation framework for multi-occupied residential buildings, with categories and responsibilities of its own. Some foundational provisions are in force; other duties are commencing in stages. Check the current position for the property on the date of the decision.
Current fire safety duties continue while the new framework is introduced. Identify the Responsible Person under the Regulatory Reform (Fire Safety) Order 2005, keep the fire risk assessment current and act on its findings. English registration, safety case and Building Assessment Certificate processes are not the Welsh route.
What residents should receive
Welsh Government remediation guidance sets expectations for regular updates, named responsibilities, understanding residents' needs and chances to raise concerns. It also covers access, noise, natural light, ventilation, security and disruption. Those managing qualifying residential remediation should plan and record how the guidance has been considered, whatever the funding route.
Residents should know who manages the remediation, who deals with fire safety and where complaints go. Offer ways to communicate that do not depend on an online account. Explain proposed changes and the reasons for them, with advance notice of access or service disruption.
Funding and your next steps
Welsh guidance describes remediation routes for residential buildings of 11 metres and over through developer commitments, social sector routes and the Welsh Building Safety Fund. Eligibility and funded scope need checking, and construction-related fire safety defects are treated differently from maintenance and leaseholder actions. Avoid promising that every item found in a survey will be funded.
Questions for a Welsh project
Has the developer accepted responsibility? Has the building entered the Welsh programme? Which surveys and approvals are needed, and who holds each project role? Keep urgent safety measures moving alongside the funding discussion, and do not apply English leaseholder protections to Welsh leases automatically.
Pre-Construction Services Agreements Building standards servicesInvestigation and design evidence
Every national route needs reliable information about the building and the proposed work. The documents and legal tests differ, but the practical question is the same: can the team explain what exists, what will change and why the solution is right for the building?
An investigation brief tied to decisions
Existing drawings help, but concealed defects, earlier alterations and differences between elevations can change the design. Ask the team which questions need answering before a specification or cost can be relied on.
For a façade, that may include the wall build-up, cavity barriers, support and fixing arrangements, compartment lines and interfaces with windows, roofs and balconies. Internal investigation may be needed as well as external opening up. Identify access restrictions, occupied areas and any asbestos or structural risks before investigation begins.
Our building surveys guide explains the methods and their limitations, and façade inspections can establish the scope of further investigation.
When information remains uncertain
Make limitations visible. Explain what has been investigated, what could not be verified and how any remaining assumptions will be tested and controlled. In England, the BSR considers unavoidable assumptions in existing-building applications case by case. Scottish and Welsh teams justify their proposals through their own application requirements.

Drawings tell you what a building should be. Opening up tells you what it is. We design remediation from what we find, and we keep that evidence so every decision can be checked later.
Associate Director, Design & Technical, Starfish Construction
Evidence that connects
A useful design record links each of these to the next. A recognised product or a test certificate cannot show suitability for every arrangement, so the appointed designers check the national regulations and the limitations in the evidence.
Which document does what?
Similar-sounding reports and certificates have different purposes. None of them on its own grants approval to carry out building work.
Fire risk assessment (FRA)
What it does: Assesses fire risk in the premises and how it is managed, under fire safety law.
What it does not do: It is not an assessment of the external wall in detail, and it is not building control approval.
Fire risk appraisal of external walls (FRAEW)
What it does: Assesses the fire risk of an external wall system within its stated scope, usually to PAS 9980.
What it does not do: It does not approve remediation work or certify the whole building.
EWS1 form
What it does: A form used by valuers and lenders when valuing flats in buildings with cladding.
What it does not do: It is not a whole-building life safety certificate or approval to build.
Single Building Assessment (SBA)
What it does: Scotland's assessment of risks to life from an external wall cladding system, under its own specification.
What it does not do: It is not a building warrant or proof that every defect is funded.
Completion certificate
What it does: Confirms the statutory completion route for building work has been followed in that country.
What it does not do: It does not end the owner's ongoing duties to maintain and manage the building.
Cladding Assurance Register entry
What it does: Records assessment and remediation information for a Scottish building.
What it does not do: It is not an English Building Assessment Certificate or a general safety certificate.
Fire statement
What it does: Sets out fire safety information for relevant planning applications in England (planning gateway one).
What it does not do: It is not Building Regulations approval, and planning permission does not authorise the building work.
Building Assessment Certificate (BAC)
What it does: Issued in England when the BSR is satisfied the PAP is meeting its occupation duties.
What it does not do: It is separate from a completion certificate and does not end ongoing responsibilities.
Safety and performance together
Remediation can affect moisture, thermal performance, loading, ventilation and durability as well as fire safety. Assess those effects before procurement.
Managing work in occupied buildings
Buildings remain homes, workplaces and places of care while work takes place. Combine the country's legal controls with daily arrangements for access, fire precautions, communication and inspection, so that the people managing the building and the construction team share an understanding of changing risks.
Plan around the people using the building
Before mobilisation, establish safe access and escape routes, deliveries, working areas, service interruptions and how occupied areas will be separated from construction. Review how opening up the fabric, storing materials or temporarily interrupting a system affects fire precautions and security.
Residents and building users need clear notice, a named contact and a way to report concerns. Consider language, disability, working patterns and people who cannot use digital updates. Explain what is known, what is changing and when the next update will come, and avoid promising uninterrupted services where a controlled shutdown is needed.
In England's occupied higher-risk buildings, coordinate this with AP, PAP and Responsible Person duties. In Scotland, agree the owner, housing provider or factor arrangements and fire safety controls. In Wales, coordinate current Responsible Person duties and the Welsh remediation guidance, checking any newly commenced occupation duties.
Resident and stakeholder engagement guideResidents and communities

Changes need the right national route
A better-rated product, cheaper detail or faster method still needs review. Identify its effect on fire, structure, weathering and the approved design before it is ordered or installed. Procurement pressure does not settle technical suitability.
England
Before a change: Classify it under English change control, notify the BSR or obtain approval where required and update the evidence.
Scotland
Before a change: Establish whether an amendment to warrant is needed before affected work, with updated design and verification arrangements.
Wales
Before a change: Classify it under Welsh change control, notify the local authority or obtain approval where required and update the agreed documents.
Inspections before work is covered
Agree acceptance criteria, hold points, responsibilities and records. Photographs should identify the location, the detail and the relevant drawing revision. Capture defects and how they were resolved. A site diary is useful, but it cannot replace inspection evidence for concealed safety-critical work.
Concerns and immediate action
Make it easy for workers, visitors and residents to report concerns, and route them to competent people who can assess the risk, act and explain the response. Mandatory occurrence reporting applies to relevant English and Welsh work, to different authorities and deadlines. Scottish projects use the notifications that apply to their warrant and other duties.
If there is immediate danger, protect people and get emergency help and competent advice. Reporting a concern is not a reason to delay necessary protective action.
Completion and building information
Decide what evidence completion will need before construction starts. The national completion routes differ, but every owner needs a reliable record of the completed work and the information required to maintain it.
England: Gateway 3
A completion process with the BSR: final documents, declarations and a handover statement, then a BSR assessment and inspection before the completion certificate is issued.
Scotland: warrant work
The Relevant Person submits the completion certificate; the verifier accepts or rejects it after reasonable inquiry.
Wales: higher-risk building work
Apply to the building control authority for full or partial completion under the Welsh process.
Check how occupation, partial completion or temporary use is handled for the actual project. A contractual practical completion milestone does not replace the statutory outcome.
The record the next team needs
Include final drawings, specifications, installed products, specialist reports, inspection and test records, approved changes and maintenance instructions. Identify retained elements, access requirements and outstanding actions, and make clear where each record sits in the building.
Handover covers access and control as well as files. Confirm that the owner, factor, facilities team or statutory duty holder can open the records, understand them and keep them current. Agree who owns that task once the contractors leave.
Golden thread and Scottish records
England and Wales have specific digital golden thread requirements for higher-risk buildings. Scotland requires the records and evidence that apply to its warrant, completion and management processes, and the CPA promotes planned compliance evidence. One consistent digital system can serve all three countries if the national requirements are kept distinct.

A good handover starts at design stage. If every change, product and inspection is recorded as the work goes in, the people who manage the building receive a record they can actually use.
Associate Director, Design & Technical, Starfish Construction
Safety management continues after completion
In England, update the occupied building's safety arrangements, risk assessments and safety case as required. In Scotland, pass the information needed for inspection and management to the owners, housing provider or factor. Address any SBA actions. In Wales, complete the Responsible Person handover and track commencement of the occupation framework.
Building surveys guide Golden thread and survey recordsPlanning your next step
Bring together the building's country, your role, the proposed work and the gaps in evidence. You do not need a complete information pack to begin, but you do need a clear question and an agreed owner for the next action.
England
Record the building work and occupation classifications, the approval category, principal appointments and any AP and PAP arrangements. Agree the route to BSR approval, change control, reporting, completion and handover.
Scotland
Confirm warrant requirements, the Relevant Person and verifier, any CPA arrangements and the investigation and evidence plan. For cladding, establish SBA status, developer or funding involvement and what remains with the owners.
Wales
Confirm the higher-risk building test, application history and transitional position. Record Part 2B appointments, submission arrangements, change control, reporting and completion. Check the funding route and which occupation duties have started.

Your role
- Owner or asset director: ask for a written approval strategy, an investigation brief and a programme that includes regulatory decisions. Understand what you remain responsible for, what you will sign and what completion evidence you will receive.
- Managing agent or factor: clarify your authority, instructions and escalation route, identify the owners and duty holders and make sure no safety action falls between the contractor, client and property team.
- Surveyor or project adviser: challenge gaps between scope, appointments, evidence and approval route, and check that a design change has reached the right national process before it becomes a procurement decision.
- Facilities team or building operator: plan service interruptions, access and checks, keep safety arrangements current during the work and confirm who will receive the final information.
- Resident or leaseholder: ask who manages building safety and the works, how you will receive updates and where to raise concerns, and take advice before alterations that could affect fire or structural safety.
Questions for the first meeting
Mistakes to avoid
Treating a funding award, planning decision, submitted application or contract variation as approval to carry out the work. Copying an English form or deadline into a Scottish or Welsh project without checking it. Finding out at handover that concealed work has no evidence.
Where there is a serious safety concern, deal with the risk while the longer approval or funding process is organised. Our insight on de-risking projects through a PCSA explains how early involvement turns these questions into a defined brief.
Speak to a specialist Building Safety Act servicesBuilding safety questions we are often asked
What are Gateways 1, 2 and 3?+
They are the three decision points for higher-risk building work in England. Gateway 1 considers fire safety at the planning stage. Gateway 2 is the building control approval application, which the BSR must approve before work starts. Gateway 3 is the completion process: the BSR assesses the final evidence and inspects the work before issuing a completion certificate. Scotland uses building warrants instead, and Wales has its own higher-risk building procedures run by local authorities.
Does the Building Safety Regulator cover England, Scotland and Wales?+
The BSR building control and occupied higher-risk building processes in chapter 03 apply in England. The BSR also has wider functions for the building control profession, including in Wales. Scotland and Wales use their own approval systems for building work.
Is a building over 11 metres a higher-risk building?+
No single 11 metre rule answers every question. The figure appears in Scottish compliance guidance, the Scottish cladding programme, Welsh funding and English leaseholder protections, each for a different purpose. Check the country, the purpose, the measurement method and the other criteria.
Can one organisation hold several project roles?+
Yes, where the law allows it and the organisation is competent and properly appointed. Keep each appointment explicit. A CDM appointment does not automatically create a Building Regulations role or transfer the client's or owner's own duties.
Are occurrence reporting deadlines the same in England and Wales?+
No. In England, the written report goes to the BSR within ten calendar days. In Wales, it goes to the building control authority within ten working days. Both need prompt initial notification. Scottish projects follow the requirements that apply to their own duties.
Does an EWS1 form replace a fire assessment or approval?+
No. An EWS1 form is used for valuation and lending. It is not a whole-building life safety certificate or approval to build, and a Scottish SBA has a different purpose again. Ask which assessment, approval and completion records the property actually needs.
Will remediation funding pay for everything?+
Eligibility and funded scope depend on the country, the building, the defect and the route. Maintenance, consequential work and ineligible defects can sit outside a funded package, and application windows can close. Get written scope and cost advice before telling owners that all work is covered.
What should happen if a resident raises a concern?+
Record and assess it, act on any immediate risk and explain the next step. Start with the building's owner, housing provider, agent or factor and the project contact. In England's occupied higher-risk buildings, the PAP complaints process and BSR escalation route apply. In an emergency, follow the building's emergency instructions and call the emergency services.
How can I check whether a new duty is already in force?+
Use the current legislation, its commencement provisions and official guidance. A consultation, a professional recommendation or a provision that has not yet commenced does not create the same immediate duty. Scotland's CPA, the Building Safety (Wales) Act 2026 and England's proposed remediation Bill each have a different legal status.
Building safety work in practice

Remediating five occupied residential blocks, Manchester
Unsafe façade and balcony materials across five residential blocks with more than 400 homes, with residents staying at home throughout.
Technical surveys, façade engineering, phased remediation and re-engineered balconies, supported by the Building Safety Fund and a resident communication programme.
An 18-month programme of remediation, sequenced so that residents could continue their daily routines.

Façade and window remediation under the Building Safety Act, Solihull
A former office block converted into 32 apartments needed façade and window remediation to a stringent client specification, including off-site testing.
Appointed principal contractor, with design by our Building Design division and structural checks by a specialist façade structural engineer. We installed 410 m² of aluminium spandrel panels and reinstated the windows.
Delivered over a 19-week programme, with residents kept informed throughout.

Student accommodation façade replacement, Bournemouth
Replacing the cladding on a student accommodation building in an exposed coastal location, where intrusive surveys revealed more complex detailing behind the existing façade.
Engineered a replacement cladding system and external fire strategy, with five full-scale BS 8414 fire tests before the design and fixing solution were accepted.
6,000 m² of façade replaced over 18 months, coordinated through 40 design team meetings.
These examples illustrate project practice. They do not show that a particular statutory approval or certificate applied unless the project record confirms it.
More on building safety
Sources and further reading
- UK Government: Building Safety Regulator, about us
- UK Government: Criteria for being a higher-risk building
- UK Government: Building control approval for higher-risk buildings
- UK Government: Preparing information for a building control approval application
- UK Government: Design and building work, meeting building requirements
- UK Government: Making changes to a higher-risk building project
- UK Government: Submitting mandatory occurrence notices and reports
- UK Government: Fire safety and high-rise residential buildings (planning gateway one)
- UK Government: Applying for a completion certificate
- UK Government: The golden thread
- UK Government: Accountable persons in high-rise residential buildings
- UK Government: Preparing a Building Assessment Certificate application
- UK Government: Residential PEEPs factsheet
- UK Government: Funding for buildings under 11 metres
- UK Government: Understanding fire risk appraisals of external walls
- legislation.gov.uk: Building Safety Act 2022, Part 4
- HSE: Commercial clients under CDM 2015
- RICS: Cladding and EWS1 frequently asked questions
- Scottish Government: Building standards
- Scottish Government: Building standards procedural handbook (warrants)
- Scottish Government: Building standards procedural handbook (completion)
- Scottish Government: Compliance Plan Approach industry guidance
- Scottish Government: Single Building Assessment specification
- Scottish Government: Fire safety guidance for existing high-rise domestic buildings
- mygov.scot: Cladding remediation Single Open Call
- legislation.gov.uk: Housing (Cladding Remediation) (Scotland) Act 2024
- Welsh Government: Building control approval for higher-risk buildings
- Welsh Government: Transitional arrangements from 1 July 2026
- Welsh Government: Design and building work duties
- Welsh Government: Mandatory occurrence reporting
- Welsh Government: Building Safety (Wales) Act 2026
- Welsh Government: Welsh Building Safety Fund remediation guidance
- Welsh Government: Resident-focused remediation guidance
- UK Parliament: Building Safety (Remediation of Unsafe Cladding etc.) Bill
About this guide
Prepared for Starfish Construction from official national guidance, current legislation and the company's technical and project material. Technical review by Joe Fay, Pre-Construction Compliance & Building Safety Director, with contributions from Joe Hulley and Halid Ibrulj, Associate Directors, Design & Technical.
Last reviewed November 2026. Building safety law and guidance are changing quickly in all three countries, so this guide will be reviewed every quarter, next by February 2027 or sooner if a material change affects the steps it describes.
Detailed coverage is for England, Scotland and Wales. This guide is general information, not legal advice, and cannot decide a building's legal classification. Get competent advice on the particular property, use, work and legal role.

Tell us the country, the building's use, the proposed work and the decision you need help with. We can help establish the available information, identify investigation needs and coordinate design and delivery for building envelope work. Our responsibilities depend on the agreed appointment.