Building works and open doors.
Writing for i-FM, Mike Leonard sets out how facilities managers and main contractors can keep commercial, healthcare, education and multi-tenant buildings safe and fully operational while major refurbishment and remediation works take place.
i-FM
16 October 2026
Facilities management, Live building works, Building Safety Act
i-FM Feature at a Glance
Facilities teams can rarely pause a building for major works. Mike explains why construction sequencing has to be planned around how the building actually operates, drawing on Premier Inn Wandsworth and Winchester Mews, where hotels, shops, homes, an NHS surgery and a leisure centre all stayed open during the work.
Three key takeaways
Plan the works around the building
Noise, dust, vibration, access changes and service shutdowns all affect the people using a live building. Phased delivery plans agreed with the FM team keep entrances, escape routes and core services working throughout.
Handover information is part of the job
Clear, verified records of installed materials, structural fixes and fire stopping reduce the burden on FM teams. Early involvement through a Pre-Construction Services Agreement lets intrusive surveys and digital information protocols start before work begins.
Use opened-up works to improve performance
When external walls or roofs are already opened up for remediation, insulation, airtightness and repair work can be coordinated in the same programme, cutting energy demand and avoiding a second round of disruption later.
MIKE LEONARD
PROJECTS DIRECTOR (MANCHESTER)
STARFISH CONSTRUCTION
Premier Inn Wandsworth, London
As highlighted by Mike, Starfish Construction acted as principal contractor with contractor design responsibility on a live hotel with ground-floor shops. Works were phased by elevation, with entrances, pedestrian routes and escape routes protected, so the hotel and retailers stayed open throughout.
Read the full article
The complete feature, including Mike's guidance on the Building Safety Act for commercial and public assets, decarbonisation through strategic retrofit and contractor and FM collaboration, is published on the i-FM website.
Insights and Guides
More expert insight from the Starfish Construction team.
De-risking Projects: PCSA & Commercial Leadership
How PCSA and strong commercial leadership help de-risk building projects, supporting compliance, cost control and delivery.
The Complete Guide to Building Envelope Performance
How the building envelope affects safety, energy, moisture and comfort, how performance is assessed and how to plan retrofit and remediation that supports compliance.
Planning major works in a live building?
Talk to our team about phasing, access planning and pre-construction support that keeps your building open and safe.